2022

     

CTH GV Area - North of STH 172

  Construction in the Monroe Road (CTH GV) area consists of sanitary sewer, water main, storm sewer, storm water management, sidewalk, curb & gutter, roadway and traffic control improvements at Monroe Road (CTH GV) intersection.

Two Week Outlook:
Week of 11/07/22:
> Signage - Costco Way North & South, Monroe Rd. and Town Hall Rd.
> Street Lights - Monroe Rd.

Week of 11/14/22:
> Signage - Costco Way North & South, Monroe Rd. and Town Hall Rd.

Traffic Control/Lights:
> To be determined based on material delivery

Road Closures, Vehicles & Traffic:
The new roads will be closed during the construction until the asphalt layers are in place. Note the ‘Important Dates’ for these schedules and updates. Landmark Boulevard, Lime Kiln Road and Monroe Road will be open during this time. Travel through the area will be possible, but delays are likely due to construction equipment using the area. Be attentive of construction workers directing traffic through the construction zone.

Resident Access:
Local resident access in this area will remain as much as possible during construction. If you have any concerns with traffic, please contact the project inspector, Cedar Corporation if you require special access needs. Also, during the connection to the existing water main, there may be times the water supply is turned off, the local businesses will be notified by the Contractor.

Communication:
It is the intent of the Village to minimize the amount of disruption and inconvenience to the community during any construction process. If during normal work hours you feel something went unnoticed, or needs attention, please contact Cedar Corporation. As project inspector, Cedar Corporation is most familiar with the daily operations of construction and can resolve many issues quickly.

If something happens after normal work hours that you feel requires immediate attention, please contact Eric Woodke at (920) 593-5518 and arrangements will be made to resolve the issue. As always, in an emergency, please call 911.

Please keep an eye on the Village website for construction updates regarding the project schedules, closures and traffic changes. Additional information is available on the Village website.

Project Updates: Construction updates will be posted on the Village website bi-weekly, and when major changes will be occurring. If at any time you would like additional information, please call Brandon Whipple at (920) 785-7308 or Thad Majkowski at (920) 785-7302 with Cedar Corporation.           
  Construction Timeline: June 2022 - December 2022 

2022

     

Allouez Ave Sidewalk

  Extension of sidewalk from Allouez Ave West to the East River Trail. This location is just South of the Rite Place on Allouez Ave.
  Target Completion: Fall 2022 