Project Coming Soon.....
Ontario-Huron Pedestrian Trail
Project Description:
As the Village continues to add residential housing in the eastern portion of Bellevue, there is a need for additional recreational amenities. One amenity which has been included in all Comprehensive Outdoor Recreation Plans since 2011 is a pedestrian trail that connects Ontario and Huron Rd. to the north of JJ. A trail in this location would connect highly saturated residential areas around the Whispering Willow subdivision with the Huron Rd trail as well as other amenities like Bellin and the YMCA.
Project Overview:

Project Timeline/Schedule:
- Operational Planning Meeting: January 28th, 2026
- 30% Plan Review: January 28th, 2026
- 1st Public Informational Meeting: February 25, 2026
- Environmental Document: March/April 2026
- 60% Plan Review, Design Study Report: April 2026
- Right of Way Plat & Descriptions: April 2026
- 2nd Public Involvement Meeting: June 2026
- 90% PS&E: September 1, 2026
- Final PS&E: November 1, 2026
- Letting Date: March 2027
- Begin Construction: Summer 2027
Public Information Meeting
Wednesday February 25, 2026
5:00 - 6:00PM
Village Hall Training Room - 3100 Eaton Rd
Public Information Meeting Letter
2026-30 CIP Ontario-Huron Cutsheet
30% Draft Plan